Raising a dam starts by building a strong base

A look at some of the prep work needed before raising Gross Dam can begin.

Adding a second floor to an older house can be tricky. 

The existing foundation, walls and floors need to be strengthened so new connection points can seamlessly meld the original structure with the new addition. The work requires careful planning, preparation and time to get ready.

At Denver Water’s Gross Dam in Boulder County, a much larger and more complex renovation is underway as the utility that serves 1.5 million people in metro Denver continues work on raising the height of the existing dam by 131 feet. 


Join people with a passion for water, at denverwater.org/Careers.


The higher dam will nearly triple the storage capacity of Gross Reservoir. The project includes making the dam wider and thicker so it can support the new height.

Excavation and foundation work began in the spring of 2022 with Denver Water preparing the face of the dam and the canyon walls for the addition of new concrete that will enlarge the dam. The actual process of raising the dam is expected to begin in 2024 after the foundation is modified and strengthened.

Image
Work on the left side of Gross Dam shows the excavation area where the dam will be raised. The actual process of raising the dam will begin in 2024. Photo credit: Denver Water.

“Foundation development is perhaps the most important part of dam construction,” said Doug Raitt, Denver Water’s construction manager for the Gross Reservoir Expansion Project. 

“There’s a lot of site development and preparation that has to be done before we can start going up. We don’t take any shortcuts and that’s why the process takes a long time.”

Image
Raising the dam involves preparing the foundation and adding concrete to make the dam wider and thicker to support the new height. Image credit: Denver Water.

Image
Once completed, the new dam will be 471 feet tall. The left and right sides of this computer rendering show the areas where excavation and concrete placement is underway. Image credit: Denver Water.

For civil engineers, the foundation of a dam includes the bottom of the structure and also the sides. The areas where the dam connects to the canyon walls on either side are called the abutments. 

At Gross Dam, crews began preparing the abutments for new concrete when the expansion project began in April 2022, using explosives to blast away rock where the new sections of the dam will be built.

Last summer and fall, crews began placing new concrete to fill in areas of the foundation where engineers determined strengthening of the rock surface was required. This filler concrete is needed to shore up the rock before new concrete, which will form the new part of the dam, is put in place.

Image
Construction workers celebrate the first concrete placement for the Gross Reservoir Expansion Project on the dam’s left abutment on Aug. 24, 2022. Photo credit: Denver Water.

“We have a team of geologists and geotechnical experts who spent two and a half years evaluating the site prior to construction and they also evaluate the rock during the excavation process,” Raitt said. 

“We’re placing new concrete to replace the rock that was removed because the type of granite we found didn’t meet the strength requirements that our structural designers required.”

Image
A team of geologists and geotechnical experts study the rock on the left abutment of Gross Dam. Photo credit: Denver Water.

Raitt said the dam’s left abutment will need around 18,000 cubic yards of concrete to replace the rock that was removed, while the right abutment will need around 4,000 cubic yards of concrete. 

(In dam terminology, the left and right abutments are named from the perspective of someone standing on the top of a dam, their back to the reservoir, and looking downstream.) 

Image
Construction workers use a large boom (in red) to place concrete on the left abutment of Gross Dam. Photo credit: Denver Water.

The type of rock and the steepness of the canyon is different on each side of the dam, so each side requires a different approach to preparing the foundation. Raitt said the type of rock also changes with the elevation of the formations.

Image
The green squares are anchor plates attached to 20-foot-long bolts that were drilled and grouted into the rock to provide additional strength. Different colors mark different types of granite in the rock formation. Photo credit: Denver Water.

The dam’s right abutment required a number of 20-foot-long bolts to be drilled into the rock and anchored in to provide additional strength before the new concrete is placed.

Raitt said the foundation concrete placement work should be completed this year.

Image
Concrete is placed in areas where rock was removed from the canyon walls because the rock wasn’t considered strong enough to support the new dam. Photo credit: Denver Water.

Hydrodemolition

Another project that started at the dam during 2022 is called hydrodemolition. The process involves using water under ultrahigh pressure to blast the top 2-3 inches of concrete from the face of the dam.

Hydrodemolition is done to rough up the surface to make sure new concrete adheres to the existing dam structure.

The specialized work is being done by WALO International, a civil engineering construction company. 

Crews completed about 60% of the work in 2022, and the goal is to finish hydrodemolition this summer. 

Image
Hydrodemolition done to the face of the dam involves construction workers blasting water under ultrahigh pressure to remove 2-3 inches of concrete to prepare the surface for future concrete. Photo credit: Denver Water.

Check out grossreservoir.org for the latest information and additional details about the Gross Reservoir Expansion Project.